Pengendalian Biaya dan Waktu Proyek Cafe Mob Tulungagung dengan Metode Earned Value

Wahyudiono, Heri Pengendalian Biaya dan Waktu Proyek Cafe Mob Tulungagung dengan Metode Earned Value.

[img] Text
7. Abstrak Pengendalian Biaya dan Waktu Proyek Cafe Mob Tulungagung dengan Metode Earned Value_Heri Wahyudiono_2022.pdf

Download (15kB)
[img] Text
7. Abstrak Pengendalian Biaya dan Waktu Proyek Cafe Mob Tulungagung dengan Metode Earned Value_Heri Wahyudiono_2022.docx

Download (31kB)
[img] Text
7. BAB I.pdf
Restricted to Repository staff only

Download (15kB)
[img] Text
7. BAB I.docx
Restricted to Repository staff only

Download (17kB)

Abstract

The aim of this research is to evaluate the cost and time utilization in the Café MOB Construction Project. The methodology employed in this study is the earned value analysis, which assesses the trends of schedule variance and cost variance during the project implementation. The project completion is evaluated by analyzing the BCWP (Budgeted Cost of Work Performed) of Rp. 812,421,675.04, BCWS (Budgeted Cost of Work Scheduled) of Rp. 467,567,357.06, and ACWP (Actual Cost of Work Performed) of Rp. 673,454,644.54. Based on a positive cost variance (CV > 0) and a cost performance index (CPI > 1), it can be concluded that the project's cost completion (EAC) reached 68% of the planned budget, amounting to Rp. 3,051,142,424.09. Furthermore, from the project schedule perspective, there was a reduction of 47% in the planned duration from 16 weeks to 9.45 weeks, as indicated by the schedule performance index (SPI > 1). Keywords: Earned Value Analysis, Cost Variance, Schedule Performance Index

Item Type: Article
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Fakultas Teknik > Prodi Teknik Sipil S1
Depositing User: NR Nurul Huda
Date Deposited: 06 Jul 2023 09:38
Last Modified: 13 Jul 2023 06:49
URI: http://repository.unik-kediri.ac.id/id/eprint/594

Actions (login required)

View Item View Item